Project Scope : Installation, Commissioning & Testing (IC&T) of AC UPS and DC Chargers for Upstream Gas Infrastructure (EUR 180 M) at BP Khassan
Industry : Oil & Gas
Dedicated Team : 5 Engineers

Project Highlights

Led the installation, commissioning, and integration of critical AC UPS and DC charger systems supporting upstream gas field operations. Oversaw on-site construction activities, installation management, and technical supervision of multidisciplinary teams to ensure compliance with engineering standards and project specifications. Coordinated closely with the client and EPC contractor, providing progress reporting, technical clarifications, and proactive issue resolution. Enforced strict HSE standards and permit-to-work compliance, maintaining a zero-incident record throughout execution. Executed comprehensive QA/QC documentation, installation checklists, and inspection test plans to align with project quality benchmarks. Managed and witnessed Factory Acceptance Testing (FAT), Site Acceptance Testing (SAT), and final commissioning verification, ensuring seamless energization and handover to operations.

Outcomes

Achieved all project milestones on schedule and ensured robust system reliability under harsh field conditions, supporting uninterrupted power availability for critical infrastructure.

Technologies Used

AEG UPS/DC Chargers, FAT/SAT Testing Procedures, Electrical Commissioning Tools, QA/QC Systems, and Field Validation Protocols.